Rowland Solar II
BetaSuspendedSolarERCOTLBNL
202.81 MW generation in Fort Bend, TX · In queue since December 2020
202.81 MW
Capacity
1
Components
Solar
5y 3m
In Queue
IA Executed
IA Status
Signed Sep 2020
Interconnection Timeline
Total Duration
5y 3m
Suspended75%
Queue EntryDec 23, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 23, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Fort Bend
Region
ERCOT
Developer
Cutlass Solar II LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 44005 WAP - 44090 Cedar Creek
Data Source
LBNL