Pachanga Wind
BetaActiveWindERCOTLBNL + Live
300 MW generation in Cameron, TX · In queue since February 2021 · Proposed COD April 2030
300 MW
Capacity
1
Components
Wind
5y 1m
In Queue
Facility Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
9y 2m
Facilities Study50%
Queue EntryFeb 9, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-04-08
Project Details
State
TX
County
Cameron
Region
ERCOT
Developer
Pachanga Wind LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 5966 Palmito - 80137 Stewart Rd
Data Source
LBNL + Live
No news available for this project.