Anson BAT — Project Summary

Queue ID
ERCOT-22INR0457
Capacity
150.6 MW
Technology
Battery
Status
active
Location
Jones, TX
Region
ERCOT
Developer
Anson II Storage LLC
IA Status
IA Executed

Anson BAT

ERCOT-22INR0457BetaActiveBatteryERCOTLBNL + Live

150.6 MW storage in Jones, TX · In queue since December 2020 · Proposed COD December 2027

150.6 MW

Capacity

1

Components

Battery

5y 4m

In Queue

IA Executed

IA Status

Signed Aug 2024

Interconnection Timeline

Queue → IA

3y 8m

IA → COD

3y 4m

Total Duration

3y 8m

Construction75%
Queue EntryDec 3, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 15, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

TX

County

Jones

Region

ERCOT

Developer

Anson II Storage LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345 kV 68004 Phantom Hill station

Data Source

LBNL + Live

No news available for this project.