DR Solar — Project Summary

Queue ID
ERCOT-22INR0454
Capacity
36 MW
Technology
Solar
Status
active
Location
Culberson, TX
Region
ERCOT
Developer
Delaware Ranch Solar, LLC
IA Status
IA Executed

DR Solar

ERCOT-22INR0454BetaActiveSolarERCOTLBNL + Live

36 MW generation in Culberson, TX · In queue since December 2020 · Proposed COD December 2026

36 MW

Capacity

1

Components

Solar

5y 4m

In Queue

IA Executed

IA Status

Signed Feb 2022

Interconnection Timeline

Queue → IA

1y 2m

IA → COD

4y 10m

Total Duration

1y 2m

Construction75%
Queue EntryDec 22, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 7, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-16

Project Details

State

TX

County

Culberson

Region

ERCOT

Developer

Delaware Ranch Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Delaware River SW (11112)

Data Source

LBNL + Live