DR Solar
ERCOT-22INR0454BetaActiveSolarERCOTLBNL + Live
36 MW generation in Culberson, TX · In queue since December 2020 · Proposed COD December 2026
36 MW
Capacity
1
Components
Solar
5y 4m
In Queue
IA Executed
IA Status
Signed Feb 2022
Interconnection Timeline
Queue → IA
1y 2m
IA → COD
4y 10m
Total Duration
1y 2m
Construction75%
Queue EntryDec 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 7, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-12-16
Project Details
State
TX
County
Culberson
Region
ERCOT
Developer
Delaware Ranch Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Delaware River SW (11112)
Data Source
LBNL + Live
No news available for this project.