SPC Bloom BESS
BetaActiveBatteryERCOTLBNL + Live
100 MW storage in Victoria, TX · In queue since December 2020 · Proposed COD April 2027
100 MW
Capacity
1
Components
Battery
5y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 4m
Facilities Study50%
Queue EntryDec 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-07
Project Details
State
TX
County
Victoria
Region
ERCOT
Developer
BRP Blue Topaz 2, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
8911 Black Bayou 138kV
Data Source
LBNL + Live