Liberty Senate Solar 1
BetaActiveSolarERCOTLBNL
202 MW generation in Jack, TX · In queue since March 2021 · Proposed COD October 2025
202 MW
Capacity
1
Components
Solar
5 years
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 7m
Schedule
5 months past proposed COD
Facilities Study50%
Queue EntryMar 1, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-27
Project Details
State
TX
County
Jack
Region
ERCOT
Developer
Senate Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
1445 Burwick 345kV
Data Source
LBNL
No news available for this project.