TORMES SOLAR — Project Summary

Queue ID
ERCOT-22INR0437
Capacity
382.12 MW
Technology
Solar
Status
active
Location
Navarro, TX
Region
ERCOT
Developer
BDPU Solar Tormes LLC
IA Status
IA Executed

TORMES SOLAR

ERCOT-22INR0437BetaActiveSolarERCOTLBNL + Live

382.12 MW generation in Navarro, TX · In queue since October 2020 · Proposed COD March 2027

382.12 MW

Capacity

1

Components

Solar

5y 6m

In Queue

IA Executed

IA Status

Signed Apr 2024

Interconnection Timeline

Queue → IA

3y 6m

IA → COD

2y 11m

Total Duration

3y 6m

Construction75%
Queue EntryOct 23, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementApr 10, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-03-31

Project Details

State

TX

County

Navarro

Region

ERCOT

Developer

BDPU Solar Tormes LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 1906 Venus - 68091 Navarro

Data Source

LBNL + Live

No news available for this project.