LUBIO SOLAR
ERCOT-22INR0426BetaActiveSolarERCOTLBNL + Live
54.47 MW generation in Kaufman, TX · In queue since October 2020 · Proposed COD April 2028
54.47 MW
Capacity
1
Components
Solar
5y 6m
In Queue
IA Executed
IA Status
Signed Nov 2024
Interconnection Timeline
Queue → IA
4y 1m
IA → COD
3y 5m
Total Duration
4y 1m
Construction75%
Queue EntryOct 7, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 8, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-04-20
Project Details
State
TX
County
Kaufman
Region
ERCOT
Developer
BDPU Solar Lubio LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 2727 Crandall - 2724 Kaufman Northwest
Data Source
LBNL + Live
No news available for this project.