Quela BESS
BetaActiveBatteryERCOTLBNL + Live
301.41 MW storage in Bexar, TX · In queue since September 2020 · Proposed COD December 2027
301.41 MW
Capacity
1
Components
Battery
5y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 3m
Facilities Study50%
Queue EntrySep 25, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Bexar
Region
ERCOT
Developer
BRP Quela BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 5110 J.T. Deely - 5294 Martinez