Ferdinand Grid BESS
201.2 MW storage in Bexar, TX · In queue since March 2021 · Proposed COD May 2026
201.2 MW
Capacity
1
Components
Battery
5y 1m
In Queue
IA Executed
IA Status
Signed Nov 2022
Queue → IA
1y 8m
IA → COD
3y 6m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-01
State
TX
County
Bexar
Region
ERCOT
Developer
Ferdinand Grid, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5260 Leon Creek 138kV
Data Source
LBNL + Live
Linked EIA Plant
Ferdinand Energy Center
EIA Plant ID: 68915