BRP Pular BESS — Project Summary

Queue ID
ERCOT-22INR0408
Capacity
233.1 MW
Technology
Battery
Status
active
Location
Hidalgo, TX
Region
ERCOT
Developer
BRP Pular BESS LLC
IA Status
Facility Study

BRP Pular BESS

BetaActiveBatteryERCOTLBNL

233.1 MW storage in Hidalgo, TX · In queue since September 2020 · Proposed COD December 2027

233.1 MW

Capacity

1

Components

Battery

5y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 3m

Facilities Study50%
Queue EntrySep 11, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

TX

County

Hidalgo

Region

ERCOT

Developer

BRP Pular BESS LLC

Utility

Entity

ERCOT

Point of Interconnection

8963 Hidalgo Energy Center 138kV

Data Source

LBNL

No news available for this project.