Dragan Storage
BetaActiveBatteryERCOTLBNL + Live
408.3 MW storage in Comanche, TX · In queue since August 2020 · Proposed COD February 2026
408.3 MW
Capacity
1
Components
Battery
5y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 6m
Schedule
1 months past proposed COD
Facilities Study50%
Queue EntryAug 21, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-28
Project Details
State
TX
County
Comanche
Region
ERCOT
Developer
Hecate Grid Dragan Storage LLC
Utility
—
Entity
ERCOT
Point of Interconnection
1440 Comanche 345kV
Data Source
LBNL + Live
No news available for this project.