Kalina Solar
BetaActiveSolarERCOTLBNL + Live
120 MW generation in San Patricio, TX · In queue since August 2020 · Proposed COD May 2029
120 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 9m
Facilities Study50%
Queue EntryAug 4, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-31
Project Details
State
TX
County
San Patricio
Region
ERCOT
Developer
Aurora Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
8606 Goddard 345kV
Data Source
LBNL + Live
No news available for this project.