BRP Perseus BESS — Project Summary

Queue ID
ERCOT-22INR0390
Capacity
202.5 MW
Technology
Battery
Status
active
Location
Nueces, TX
Region
ERCOT
Developer
BRP Perseus BESS LLC
IA Status
Facility Study

BRP Perseus BESS

BetaActiveBatteryERCOTLBNL + Live

202.5 MW storage in Nueces, TX · In queue since August 2020 · Proposed COD December 2027

202.5 MW

Capacity

1

Components

Battery

5y 7m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 4m

Facilities Study50%
Queue EntryAug 21, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

TX

County

Nueces

Region

ERCOT

Developer

BRP Perseus BESS LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 138 kV line from Lon Hill (#8452) to Bessel (#8060)