BRP Perseus BESS
BetaActiveBatteryERCOTLBNL + Live
202.5 MW storage in Nueces, TX · In queue since August 2020 · Proposed COD December 2027
202.5 MW
Capacity
1
Components
Battery
5y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 4m
Facilities Study50%
Queue EntryAug 21, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Nueces
Region
ERCOT
Developer
BRP Perseus BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138 kV line from Lon Hill (#8452) to Bessel (#8060)
Data Source
LBNL + Live
No news available for this project.