Cachi BESS
BetaActiveBatteryERCOTLBNL
205.46 MW storage in Guadalupe, TX · In queue since August 2020 · Proposed COD March 2025
205.46 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Status
Signed Jun 2021
Interconnection Timeline
Queue → IA
10 months
IA → COD
3y 9m
Total Duration
10 months
Schedule
12 months past proposed COD
Construction75%
Queue EntryAug 21, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 11, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-03-31
Project Details
State
TX
County
Guadalupe
Region
ERCOT
Developer
BRP Cachi BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
7680 Clear Springs 138kV
Data Source
LBNL
No news available for this project.