BRP Pictor BESS
BetaActiveBatteryERCOTLBNL + Live
201.07 MW storage in Crane, TX · In queue since July 2020 · Proposed COD November 2025
201.07 MW
Capacity
1
Components
Battery
5y 8m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 4m
Schedule
5 months past proposed COD
Facilities Study50%
Queue EntryJul 24, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-01
Project Details
State
TX
County
Crane
Region
ERCOT
Developer
BRP Pictor BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
60400 Lynx 138kV
Data Source
LBNL + Live
No news available for this project.