Razorbill Storage
BetaActiveBatteryERCOTLBNL + Live
120 MW storage in Matagorda, TX · In queue since August 2020 · Proposed COD December 2027
120 MW
Capacity
1
Components
Battery
5y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 4m
Facilities Study50%
Queue EntryAug 4, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-15
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64
Data Source
LBNL + Live
No news available for this project.