Queue ID
ERCOT-22INR0382
Capacity
120 MW
Technology
Battery
Status
active
Location
Matagorda, TX
Region
ERCOT
Developer
RWE Solar Development, LLC
IA Status
Facility Study

Razorbill Storage

BetaActiveBatteryERCOTLBNL + Live

120 MW storage in Matagorda, TX · In queue since August 2020 · Proposed COD December 2027

120 MW

Capacity

1

Components

Battery

5y 7m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 4m

Facilities Study50%
Queue EntryAug 4, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-15

Project Details

State

TX

County

Matagorda

Region

ERCOT

Developer

RWE Solar Development, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64