Inertia BESS 2
BetaActiveBatteryERCOTLBNL
100.77 MW storage in Haskell, TX · In queue since October 2020 · Proposed COD July 2027
100.77 MW
Capacity
1
Components
Battery
5y 5m
In Queue
IA Executed
IA Status
Signed May 2021
Interconnection Timeline
Queue → IA
7 months
IA → COD
6y 2m
Total Duration
7 months
Construction75%
Queue EntryOct 13, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 4, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Haskell
Region
ERCOT
Developer
Inertia Energy Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 60515 Clear Crossing - 6104 Smoky Hill
Data Source
LBNL
No news available for this project.