Loma Pinta Solar
BetaActiveSolarERCOTLBNL + Live
203.06 MW generation in La Salle, TX · In queue since June 2020 · Proposed COD May 2028
203.06 MW
Capacity
1
Components
Solar
5y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 11m
Facilities Study50%
Queue EntryJun 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-31
Project Details
State
TX
County
La Salle
Region
ERCOT
Developer
Loma Pinta Wind Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5705 Fowlerton 138kV
Data Source
LBNL + Live
No news available for this project.