XE Murat [Adlong] Solar — Project Summary

Queue ID
ERCOT-22INR0354
Capacity
60.36 MW
Technology
Solar
Status
active
Location
Harris, TX
Region
ERCOT
Developer
Liberty 1 Solar
IA Status
IA Executed

XE Murat [Adlong] Solar

BetaActiveSolarERCOTLBNL

60.36 MW generation in Harris, TX · In queue since August 2020 · Proposed COD January 2025

60.36 MW

Capacity

1

Components

Solar

5y 7m

In Queue

IA Executed

IA Status

Signed Mar 2022

Interconnection Timeline

Queue → IA

1y 7m

IA → COD

2y 10m

Total Duration

1y 7m

Schedule

14 months past proposed COD

Construction75%
Queue EntryAug 4, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMar 4, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-01-31

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

Liberty 1 Solar

Utility

Entity

ERCOT

Point of Interconnection

tap 138kV 40391 Crosby C66 - 40130 Atascocita

Data Source

LBNL