Crater BESS
BetaActiveBatteryERCOTLBNL + Live
301.17 MW storage in Howard, TX · In queue since May 2020 · Proposed COD March 2028
301.17 MW
Capacity
1
Components
Battery
5y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 10m
Facilities Study50%
Queue EntryMay 20, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
TX
County
Howard
Region
ERCOT
Developer
BRP Crater BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 1025 Falcon Seaboard - 1021 Midland East
Data Source
LBNL + Live