Matagorda Solar
ERCOT-22INR0342BetaActiveSolarERCOTLBNL + Live
101 MW generation in Matagorda, TX · In queue since May 2020 · Proposed COD August 2027
101 MW
Capacity
1
Components
Solar
5y 11m
In Queue
IA Executed
IA Status
Signed Jun 2022
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
5y 2m
Total Duration
2y 1m
Construction75%
Queue EntryMay 1, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 8, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-08-25
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
Leeward Renewable Energy Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5555 Shropshire 69kV
Data Source
LBNL + Live