Skylab Solar
BetaActiveSolarERCOTLBNL + Live
609.74 MW generation in Wharton, TX · In queue since June 2020 · Proposed COD December 2025
609.74 MW
Capacity
1
Components
Solar
5y 9m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 6m
Schedule
4 months past proposed COD
Facilities Study50%
Queue EntryJun 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
TX
County
Wharton
Region
ERCOT
Developer
EDF Renewables Development, Inc.
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 5915 STP - 8249 Angstrom
Data Source
LBNL + Live
No news available for this project.