Brantley Branch Batt
BetaActiveBatteryERCOTLBNL + Live
302.35 MW storage in Rusk, TX · In queue since May 2020 · Proposed COD February 2029
302.35 MW
Capacity
1
Components
Battery
5y 10m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 9m
Facilities Study50%
Queue EntryMay 1, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-02-01
Project Details
State
TX
County
Rusk
Region
ERCOT
Developer
Brantley Branch LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Mt. Enterprise (Bus # 3116) _x0013_ Martin Lake 345kv Line (Bus # 3100
Data Source
LBNL + Live
No news available for this project.