Lan Solar SLF
BetaActiveSolarERCOTLBNL + Live
182.2 MW generation in Lamar, TX · In queue since May 2020 · Proposed COD August 2028
182.2 MW
Capacity
1
Components
Solar
5y 10m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 3m
Pre-Study0%
Queue EntryMay 1, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-26
Project Details
State
TX
County
Lamar
Region
ERCOT
Developer
—
Utility
—
Entity
ERCOT
Data Source
LBNL + Live