Pink Solar
ERCOT-22INR0281BetaActiveSolarERCOTLBNL + Live
151.9 MW generation in Hunt, TX · In queue since January 2020 · Proposed COD July 2029
151.9 MW
Capacity
1
Components
Solar
6y 3m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
9y 6m
Pre-Study0%
Queue EntryJan 30, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-31
Project Details
State
TX
County
Hunt
Region
ERCOT
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL + Live
No news available for this project.