Clutch City Solar Phase I
ERCOT-22INR0279BetaActiveSolarERCOTLBNL + Live
200.75 MW generation in Brazoria, TX · In queue since January 2020 · Proposed COD July 2028
200.75 MW
Capacity
1
Components
Solar
6y 3m
In Queue
IA Executed
IA Status
Signed Sep 2022
Interconnection Timeline
Queue → IA
2y 8m
IA → COD
5y 10m
Total Duration
2y 8m
Construction75%
Queue EntryJan 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 30, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Brazoria
Region
ERCOT
Developer
HZ Solar I, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 42960 Mustang Bayou _x0013_ 42100 Hudson CKT #04
Data Source
LBNL + Live
No news available for this project.