Shaula II Solar
ERCOT-22INR0267BetaActiveSolarERCOTLBNL + Live
205.2 MW generation in Dewitt, TX · In queue since December 2019 · Proposed COD May 2026
205.2 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Status
Signed Apr 2022
Interconnection Timeline
Queue → IA
2y 4m
IA → COD
4y 1m
Total Duration
2y 4m
Construction75%
Queue EntryDec 18, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementApr 27, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-05-30
Project Details
State
TX
County
Dewitt
Region
ERCOT
Developer
Shaula Energy Project II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1
Data Source
LBNL + Live