Eliza Storage
BetaActiveBatteryERCOTLBNL
100.4 MW storage in Kaufman, TX · In queue since December 2019 · Proposed COD March 2025
100.4 MW
Capacity
1
Components
Battery
6y 3m
In Queue
IA Executed
IA Status
Signed Aug 2022
Interconnection Timeline
Queue → IA
2y 8m
IA → COD
2y 7m
Total Duration
2y 8m
Schedule
13 months past proposed COD
Construction75%
Queue EntryDec 3, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 4, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-03-11
Project Details
State
TX
County
Kaufman
Region
ERCOT
Developer
Ables Springs Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 2478 Royse - 3103 Shamburger
Data Source
LBNL
No news available for this project.