Shaula I Solar — Project Summary

Queue ID
ERCOT-22INR0251
Capacity
205.2 MW
Technology
Solar
Status
active
Location
Dewitt, TX
Region
ERCOT
Developer
Shaula Energy Project, LLC
IA Status
IA Executed

Shaula I Solar

ERCOT-22INR0251BetaActiveSolarERCOTLBNL + Live

205.2 MW generation in Dewitt, TX · In queue since December 2019 · Proposed COD March 2026

205.2 MW

Capacity

1

Components

Solar

6y 4m

In Queue

IA Executed

IA Status

Signed Feb 2022

Interconnection Timeline

Queue → IA

2y 2m

IA → COD

4y 1m

Total Duration

2y 2m

Schedule

0 months past proposed COD

Construction75%
Queue EntryDec 3, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 16, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-03-31

Project Details

State

TX

County

Dewitt

Region

ERCOT

Developer

Shaula Energy Project, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1

Data Source

LBNL + Live

No news available for this project.