Razorbill Solar — Project Summary

Queue ID
ERCOT-22INR0244
Capacity
240 MW
Technology
Solar
Status
active
Location
Matagorda, TX
Region
ERCOT
Developer
RWE Solar Development, LLC
IA Status
Facility Study

Razorbill Solar

BetaActiveSolarERCOTLBNL + Live

240 MW generation in Matagorda, TX · In queue since January 2020 · Proposed COD December 2027

240 MW

Capacity

1

Components

Solar

6y 2m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 11m

Facilities Study50%
Queue EntryJan 2, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-15

Project Details

State

TX

County

Matagorda

Region

ERCOT

Developer

RWE Solar Development, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64

Data Source

LBNL + Live

No news available for this project.