Rockefeller Storage — Project Summary

Queue ID
ERCOT-22INR0239
Capacity
206.8 MW
Technology
Battery
Status
active
Location
Schleicher, TX
Region
ERCOT
Developer
Mittel Rockefeller Storage LLC
IA Status
IA Executed

Rockefeller Storage

ERCOT-22INR0239BetaActiveBatteryERCOTLBNL + Live

206.8 MW storage in Schleicher, TX · In queue since October 2019 · Proposed COD June 2027

206.8 MW

Capacity

1

Components

Battery

6y 6m

In Queue

IA Executed

IA Status

Signed Sep 2024

Interconnection Timeline

Queue → IA

4y 11m

IA → COD

2y 9m

Total Duration

4y 11m

Construction75%
Queue EntryOct 31, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementSep 23, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

TX

County

Schleicher

Region

ERCOT

Developer

Mittel Rockefeller Storage LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

76003 Big Hill 345kV

Data Source

LBNL + Live

No news available for this project.