Dragan Solar — Project Summary

Queue ID
ERCOT-22INR0237
Capacity
411 MW
Technology
Solar
Status
active
Location
Comanche, TX
Region
ERCOT
Developer
Hecate Comanche Solar LLC
IA Status
Facility Study

Dragan Solar

BetaActiveSolarERCOTLBNL + Live

411 MW generation in Comanche, TX · In queue since November 2019 · Proposed COD September 2027

411 MW

Capacity

1

Components

Solar

6y 4m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 10m

Facilities Study50%
Queue EntryNov 11, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-15

Project Details

State

TX

County

Comanche

Region

ERCOT

Developer

Hecate Comanche Solar LLC

Utility

Entity

ERCOT

Point of Interconnection

1440 Comanche 345kV

Data Source

LBNL + Live

No news available for this project.