Greyhound Solar 2
BetaActiveSolarERCOTLBNL + Live
500 MW generation in Ector, TX · In queue since May 2019 · Proposed COD November 2028
500 MW
Capacity
1
Components
Solar
6y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 6m
Facilities Study50%
Queue EntryMay 14, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-17
Project Details
State
TX
County
Ector
Region
ERCOT
Developer
Greyhound Solar 2
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV dbl ckt 11010 Wolf - 1018 Moss and 11008 Wolf - 11028 Odessa
Data Source
LBNL + Live
No news available for this project.