Felix North Solar
ERCOT-22INR0209BetaActiveSolarERCOTLBNL + Live
100.54 MW generation in Wilbarger, TX · In queue since January 2019 · Proposed COD December 2028
100.54 MW
Capacity
1
Components
Solar
7y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 11m
Facilities Study50%
Queue EntryJan 17, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
TX
County
Wilbarger
Region
ERCOT
Developer
Crescent Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6101 Riley 345kV
Data Source
LBNL + Live