Delilah Solar 1
ERCOT-22INR0202BetaActiveSolarERCOTLBNL + Live
300 MW generation in Lamar, TX · In queue since November 2018 · Proposed COD May 2026
300 MW
Capacity
1
Components
Solar
7y 5m
In Queue
IA Executed
IA Status
Signed Dec 2020
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
5y 5m
Total Duration
2y 1m
Construction75%
Queue EntryNov 20, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 22, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-05-30
Project Details
State
TX
County
Lamar
Region
ERCOT
Developer
Delilah Solar Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap both 345kV 1685 FarmersVl - 1695 Moses ckts
Data Source
LBNL + Live
No news available for this project.