Anchor Wind III
ERCOT-21INR0546BetaActiveWindERCOTLBNL + Live
16 MW generation in Eastland, TX · In queue since December 2021 · Proposed COD December 2025
16 MW
Capacity
1
Components
Wind
4y 4m
In Queue
IA Executed
IA Status
Signed Nov 2020
Interconnection Timeline
IA → COD
5y 1m
Total Duration
4y 4m
Schedule
3 months past proposed COD
Construction75%
Queue EntryDec 3, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 30, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2025-12-29
Project Details
State
TX
County
Eastland
Region
ERCOT
Developer
RANCHLAND WIND PROJECT LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Aspire Station (68011)
Data Source
LBNL + Live