Viking Solar
288.99 MW generation in Somervell, TX · In queue since October 2020 · Proposed COD July 2027
288.99 MW
Capacity
1
Components
Solar
5y 6m
In Queue
IA Executed
IA Status
Signed Oct 2022
Queue → IA
2 years
IA → COD
4y 9m
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-13
State
TX
County
Somervell
Region
ERCOT
Developer
Yellow Viking Development One, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
ap 345kV 1900 Comanche Peak - 11886 Timberview Switch
Data Source
LBNL + Live
Last updated 2026-03-26