Wolf Ridge Repower
BetaActiveWindERCOTLBNL
9 MW generation in Cooke, TX · In queue since June 2020 · Proposed COD January 2025
9 MW
Capacity
1
Components
Wind
5y 9m
In Queue
IA Executed
IA Status
Signed Nov 2007
Interconnection Timeline
IA → COD
17y 2m
Total Duration
5y 9m
Schedule
15 months past proposed COD
Construction75%
Queue EntryJun 26, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 1, 2007
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2025-01-15
Project Details
State
TX
County
Cooke
Region
ERCOT
Developer
Wolf Ridge Wind Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
730 Wolf Ridge 138kV
Data Source
LBNL
No news available for this project.