McClure Solar
105.73 MW generation in Palo Pinto, TX · In queue since June 2020 · Proposed COD December 2025
105.73 MW
Capacity
1
Components
Solar
5y 9m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
5y 6m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
State
TX
County
Palo Pinto
Region
ERCOT
Developer
McClure Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 69kV 785 Oran - 343 Morris Sheppard
Data Source
LBNL + Live
District moves forward on solar plan
LEWISTOWN — The removal of a grove of trees behind Mifflin County High School has sparked scrutiny of a solar energy project being...
This Vermont Utility Is Revolutionizing Its Power Grid to Fight Climate Change. Will the Rest of the Country Follow Suit?
Green Mountain Power, a major Vermont electric utility, is revolutionizing its power grid to fight climate change. Will others follow?
This Vermont Utility Is Revolutionizing Its Power Grid to Fight Climate Change. Will the Rest of the Country Follow Suit?
Green Mountain Power, a major Vermont electric utility, is revolutionizing its power grid to fight climate change. Will others follow?
This Vermont Utility Is Revolutionizing Its Power Grid to Fight Climate Change. Will the Rest of the Country Follow Suit?
Green Mountain Power, a major Vermont electric utility, is revolutionizing its power grid to fight climate change. Will others follow?
Last updated 2026-03-26