Angels Creek
BetaActiveBatteryERCOTLBNL
31.68 MW storage in Webb, TX · In queue since June 2020 · Proposed COD June 2026
31.68 MW
Capacity
1
Components
Battery
5y 9m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6 years
Facilities Study50%
Queue EntryJun 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
TX
County
Webb
Region
ERCOT
Developer
Angels Creek LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5888 Bruni 69kV
Data Source
LBNL
No news available for this project.