Pearl Crescent Storage
BetaActiveBatteryERCOTLBNL + Live
50.26 MW storage in Colorado, TX · In queue since December 2019 · Proposed COD December 2026
50.26 MW
Capacity
1
Components
Battery
6y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7 years
Facilities Study50%
Queue EntryDec 20, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-15
Project Details
State
TX
County
Colorado
Region
ERCOT
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Rock Island (57640) 138kV
Data Source
LBNL + Live