Independence Trail Storage
BetaActiveBatteryERCOTLBNL + Live
100 MW storage in Childress, TX · In queue since December 2019 · Proposed COD January 2028
100 MW
Capacity
1
Components
Battery
6y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 1m
Facilities Study50%
Queue EntryDec 3, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-01
Project Details
State
TX
County
Childress
Region
ERCOT
Developer
KCE TX 16, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
60501 Tesla 345kV
Data Source
LBNL + Live
No news available for this project.