Nabatoto Solar North
ERCOT-21INR0428BetaActiveSolarERCOTLBNL + Live
451.35 MW generation in Leon, TX · In queue since September 2019 · Proposed COD May 2027
451.35 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Status
Signed Feb 2021
Interconnection Timeline
Queue → IA
1y 5m
IA → COD
6y 3m
Total Duration
1y 5m
Construction75%
Queue EntrySep 23, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 26, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-05-01
Project Details
State
TX
County
Leon
Region
ERCOT
Developer
CG Leon County II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 967 Gibbons Creek - 46020 Limestone ckt 50
Data Source
LBNL + Live
No news available for this project.