Armadillo Solar
200.09 MW generation in Navarro, TX · In queue since August 2019 · Proposed COD December 2026
200.09 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
Signed Feb 2021
Queue → IA
1y 6m
IA → COD
5y 10m
Total Duration
1y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-31