Jayhawk Solar — Project Summary

Queue ID
ERCOT-21INR0414
Capacity
101.5 MW
Technology
Solar
Status
active
Location
Mitchell, TX
Region
ERCOT
Developer
Renewable Energy Ventures, LLC
IA Status
Facility Study

Jayhawk Solar

BetaActiveSolarERCOTLBNL + Live

101.5 MW generation in Mitchell, TX · In queue since August 2019 · Proposed COD October 2025

101.5 MW

Capacity

1

Components

Solar

6y 7m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

6y 2m

Schedule

5 months past proposed COD

Facilities Study50%
Queue EntryAug 5, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-30

Project Details

State

TX

County

Mitchell

Region

ERCOT

Developer

Renewable Energy Ventures, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 1030 Morgan - 76030 Gasconades

Data Source

LBNL + Live