Red-tailed Hawk Solar — Project Summary

Queue ID
ERCOT-21INR0389
Capacity
355.27 MW
Technology
Solar
Status
suspended
Location
Wharton, TX
Region
ERCOT
Developer
Red Tailed Hawk Solar LLC
IA Status
IA Executed

Red-tailed Hawk Solar

BetaSuspendedSolarERCOTLBNL

355.27 MW generation in Wharton, TX · In queue since July 2019

355.27 MW

Capacity

1

Components

Solar

6y 8m

In Queue

IA Executed

IA Status

Signed Aug 2020

Interconnection Timeline

Queue → IA

1y 1m

Total Duration

1y 1m

Suspended75%
Queue EntryJul 8, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 28, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

TX

County

Wharton

Region

ERCOT

Developer

Red Tailed Hawk Solar LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 44200 Bailey-44040 Hillje ckt 72

Data Source

LBNL

No news available for this project.