HIP Solar Project
BetaActiveSolarERCOTLBNL + Live
137.6 MW generation in Leon, TX · In queue since August 2019 · Proposed COD May 2027
137.6 MW
Capacity
1
Components
Solar
6y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 9m
Facilities Study50%
Queue EntryAug 16, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-01
Project Details
State
TX
County
Leon
Region
ERCOT
Developer
ConnectGen Operating LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 967 Gibbons Creek - 46020 Limestone ckt 50
Data Source
LBNL + Live
No news available for this project.