Eliza Solar
151.7 MW generation in Kaufman, TX · In queue since June 2019 · Proposed COD December 2025
151.7 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Status
Signed Aug 2022
Queue → IA
3y 2m
IA → COD
3y 4m
Total Duration
3y 2m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-18
State
TX
County
Kaufman
Region
ERCOT
Developer
Ables Springs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 2478 Royse - 3103 Shamburger
Data Source
LBNL + Live