Lunis Creek Solar SLF — Project Summary

Queue ID
ERCOT-21INR0344
Capacity
617.12 MW
Technology
Solar
Status
active
Location
Jackson, TX
Region
ERCOT
Developer
Lunis Creek Solar Project, LLC
IA Status
IA Executed

Lunis Creek Solar SLF

BetaActiveSolarERCOTLBNL

617.12 MW generation in Jackson, TX · In queue since May 2019 · Proposed COD December 2026

617.12 MW

Capacity

1

Components

Solar

6y 10m

In Queue

IA Executed

IA Status

Signed Oct 2021

Interconnection Timeline

Queue → IA

2y 5m

IA → COD

5y 2m

Total Duration

2y 5m

Construction75%
Queue EntryMay 2, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 29, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

TX

County

Jackson

Region

ERCOT

Developer

Lunis Creek Solar Project, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345 kV Static (#8676) - South Texas Project (#5915)

Data Source

LBNL

No news available for this project.