Lunis Creek Solar SLF
BetaActiveSolarERCOTLBNL
617.12 MW generation in Jackson, TX · In queue since May 2019 · Proposed COD December 2026
617.12 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Status
Signed Oct 2021
Interconnection Timeline
Queue → IA
2y 5m
IA → COD
5y 2m
Total Duration
2y 5m
Construction75%
Queue EntryMay 2, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 29, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Jackson
Region
ERCOT
Developer
Lunis Creek Solar Project, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345 kV Static (#8676) - South Texas Project (#5915)
Data Source
LBNL
No news available for this project.